  • 442

    2024.01.29

    The largest and heaviest module - the CA20 - has been installed at unit 1 of the Xudabao nuclear power plant in China's Liaoning province, China National Nuclear Corporation subsidiary China Nuclear Industry 23 Construction Company Limited has announced.
  • 441

    2024.01.26

    The installation of the inner and outer parts of the steel structures of the 215-tonne passive heat removal system was completed in two days on Rooppur 2 in Bangladesh, Rosatom says. 
  • 440

    2024.01.26

    GE Hitachi Nuclear Energy has been awarded a GBP33.6 million (USD42.7 million) grant to support it in developing its BWRX-300 small modular reactor in the UK. The design will now enter the Generic Design Assessment process.
  • 439

    2024.01.25

    Prime Minister Robert Golob says Slovenia's long-term use of nuclear energy "requires the broadest national and political consensus" as he announces a meeting with senior figures including opposition party leaders and members of parliament from Hungary and Italy.
  • 438

    2024.01.24

    The aim is for a first project in Canada by 2030 for a Prodigy marine-based transportable nuclear power plant featuring Westinghouse eVinci microreactors.
  • 437

    2024.01.24

    The UK's Hinkley Point C nuclear power plant, which was expected to be completed in 2027 and cost up to GBP26 billion, is now unlikely to be operational before 2030, with the overall cost revised to between GBP31 to GBP34 billion (in 2015 prices), EDF has said.
  • 436

    2024.01.23

    Egypt and Russia's presidents joined by a ceremony by videolink to mark the pouring of the first concrete into the foundation slab of El Dabaa unit 4 - a moment which means all four units at the Egyptian nuclear power plant are now under construction.
  • 435

    2024.01.23

    The GBP1.3 billion (USD1.65 billion) of government funding will be used for necessary infrastructure work such as roads and rail lines and allows construction work to continue pending a final investment decision on the proposed plant.
  • 434

    2024.01.22

    Those seeking selection for the engineering, construction, procurement and commissioning of a new AP1000 unit at the Kozloduy nuclear power plant site by 2035, have until 2 February to respond to an invitation for expression of interest.
  • 433

    2024.01.19

    The second unit at Bangladesh's first nuclear power plant has had concreting completed on its outer containment shell, in a process which took 122 days.